Chitwan. The expansion and upgrading work on the Nagdhunga–Malekhu section of the Prithvi Highway has gained momentum. So far, the paving work for 11 kilometers of this section has been completed. While eight kilometers were paved last year, an additional three kilometers have been finished this year.

Paving has now been completed in some areas of Kurintar, Phisling, Charoudi, and Bishaltar, while work is vigorously underway in the Bandare area of Dhading. According to Vijay Darai, Engineer at the Nagdhunga–Mugling Road Project (West Section), the physical progress of the project has reached 40 percent to date.

Although the contract was awarded in Poush 15, 2079 BS with a three-year completion deadline, the work was not finished on time, resulting in a six-month extension. Currently, nearly two hundred workers, staff, and technicians are engaged in the paving work.

The work of laying the base and sub-base for paving in the Phisling and Jawang Khola areas has reached the final stage. Despite the acceleration of construction work, material shortages are posing a challenge.

Although construction materials have been brought from various areas of Dhading and Ichhakamana, a shortage is anticipated for the long term. The construction side claims that work will not stop if materials are sufficient. Among the six bridges on this section, work is progressing after the foundation for the Hugdi and Charoudi bridges, and landslide prevention work is also ongoing at Krishnabhir.

This nearly 39-kilometer-long road section is being expanded with the support of the World Bank. Under this project, 2.2 kilometers of road in the Malekhu, Benighat, and Mugling areas will be six lanes wide, and 7.2 kilometers of road will be four lanes wide.

The project stated that a 3-lane 'climbing' lane will be constructed in uphill sections, and the remaining road will remain two lanes. Sharma–ZICG secured the contract for 4 billion 80 crore 59 lakh rupees.

This specific news has been automatically translated by AI. As a result, there may be some inaccuracies or language errors.

Related Articles

Nepal and Denmark Hold Third Bilateral Consultations Meeting in Kathmandu

Nepal and Denmark Hold Third Bilateral Consultations Meeting in Kathmandu

Kathmandu. The third meeting of the bilateral consultation mechanism between Nepal and Denmark has concluded...
MP Mohan Acharya Highlights Procurement Law Weaknesses Hindering Infrastructure Development

MP Mohan Acharya Highlights Procurement Law Weaknesses Hindering Infrastructure Development

Kathmandu. Nepali Congress lawmaker Mohan Acharya has stated that weaknesses in the existing Public Procurement...
Rastriya Prajatantra Party Chief Whip Khushbu Oli Questions Government's Work Style and Budget Allocation Priorities

Rastriya Prajatantra Party Chief Whip Khushbu Oli Questions Government's Work Style and Budget Allocation Priorities

Kathmandu. Rastriya Prajatantra Party (RPP) Chief Whip Khushbu Oli has questioned the government's work style...
Shram Sanskriti Party Chairman Harka Raj Rai Comments on Budget Implementation Challenges

Shram Sanskriti Party Chairman Harka Raj Rai Comments on Budget Implementation Challenges

Kathmandu. Shram Sanskriti Party Chairman Harka Raj Rai has commented that the law itself is...
Congress MP Anand Prasad Dhungana Demands Passage of Federalism Laws Within Current Session

Congress MP Anand Prasad Dhungana Demands Passage of Federalism Laws Within Current Session

Kathmandu. Chief opposition party Nepali Congress's National Assembly MP Anand Prasad Dhungana has demanded that...
Prime Minister and Ministers Absent During Budget Discussions in Parliament

Prime Minister and Ministers Absent During Budget Discussions in Parliament

Kathmandu. The tradition of the Prime Minister and ministers being absent during budget discussions in...
District Court Kathmandu Continues Hearing on Fake Bhutanese Refugee Case

District Court Kathmandu Continues Hearing on Fake Bhutanese Refugee Case

Kathmandu. The hearing of the case related to the fake Bhutanese refugee scam at the...
Parliamentary Committee Slams Minister's Absence Amidst Critical Infrastructure Debate

Parliamentary Committee Slams Minister's Absence Amidst Critical Infrastructure Debate

Kathmandu. Stakeholders complained that if the traffic system of Kathmandu Valley is not improved immediately,...