Siddhababa Tunnel Project Progresses Rapidly, Targeting Completion by Dashain

Butwal. The Siddhababa Tunnel project, under construction along the Siddhartha Highway, has achieved approximately 60 percent physical progress and 51 percent financial progress.

Project Chief Navaraj Bastola told Ratopati that construction work has accelerated significantly following the breakthrough of the tunnel.

He noted that internal works, including floor concreting and wall coating, have been completed, with all three bypasses being constructed simultaneously.

A total of 1,520 meters of tunnel lining has been completed. The invert (floor concreting) is finished, and the base for drainage on both sides has also been constructed.

siddhababa surung marga tunnel (1)

Project Chief Bastola stated that road construction inside the tunnel is expected to be completed by the end of Shrawan. The goal is to finish external works to allow vehicle movement by the upcoming Dashain.

The project was contracted to the Chinese company, China State Construction Engineering Corporation (CSCEC), for 7.3421 billion rupees, with a deadline of Chaitra 2083.

The construction company claims that over 250 workers are deployed daily. A building for inspection is under construction within the Butwal Road Office compound, and two control buildings are being built at the north and south entrances for tunnel security.

The control building will monitor activities inside the tunnel, including traffic, pollution levels, noise, and airflow, via computer screens.

siddhababa surung marga tunnel (4)

The contract includes a provision for the company to maintain the tunnel for five years after completion.

The contractor has already brought some equipment, including wiring, ventilation, and fire safety systems, while other materials are currently at the Kerung border. Diplomatic efforts are underway through the Ministry of Foreign Affairs to expedite customs clearance.

The project also includes landslide mitigation measures in the Dobhan area, such as installing rock nets and supports to prevent falling stones.

siddhababa surung marga tunnel (5)

The two-lane main tunnel will be 1,126 meters long, 10.5 meters wide, and approximately 7 meters high. Bastola mentioned that the plan is to prioritize the tunnel completion to allow traffic flow before finishing external works.

The Siddhababa section of the Siddhartha Highway is considered highly hazardous due to frequent rockfalls in winter and landslides during the monsoon, making travel between Dobhan, Palpa, and Butwal dangerous.

This specific news has been automatically translated by AI. As a result, there may be some inaccuracies or language errors.

Related Articles

Securities Board of Nepal Appoints New Chairman Dr. Gopal Bhatta

Securities Board of Nepal Appoints New Chairman Dr. Gopal Bhatta

Kathmandu. After almost 2 months, the Securities Board of Nepal has got a new leadership....
Nepal Rastra Bank Issues New Guidelines on CEO Salary and Benefits

Nepal Rastra Bank Issues New Guidelines on CEO Salary and Benefits

Kathmandu. Nepal Rastra Bank has issued new guidelines regarding the salary, allowances, and other benefits...
Nepal Begins Significant Electricity Exports to India and Bangladesh as Monsoon Arrives

Nepal Begins Significant Electricity Exports to India and Bangladesh as Monsoon Arrives

Kathmandu. With the onset of the monsoon, Nepal has started exporting electricity to India and...
National Assembly Approves Anti-Money Laundering Ordinance Amendment

National Assembly Approves Anti-Money Laundering Ordinance Amendment

Kathmandu. The National Assembly meeting on Friday approved the 'Anti-Money Laundering (Third Amendment) Ordinance, 2083'...
Government Forms Task Force to Investigate Agricultural and Livestock Subsidies

Government Forms Task Force to Investigate Agricultural and Livestock Subsidies

Kathmandu. The government has formed a five-member task force to investigate agricultural and livestock subsidies...
Government Serious About Budhi Gandaki Hydropower Project Construction, Minister Shrestha States

Government Serious About Budhi Gandaki Hydropower Project Construction, Minister Shrestha States

Kathmandu. Minister for Energy, Water Resources and Irrigation, Biraj Shrestha, has stated that the government...
Rastriya Swatantra Party MPs Question Governor on Credit Growth and Regulation

Rastriya Swatantra Party MPs Question Governor on Credit Growth and Regulation

Kathmandu. In a discussion held in the Finance Committee of the House of Representatives on...
Finance Minister States Government Prioritizes Long-Term Economic Interests Over Short-Term Stock Market Fluctuations

Finance Minister States Government Prioritizes Long-Term Economic Interests Over Short-Term Stock Market Fluctuations

Kathmandu. Finance Minister Dr. Swarnim Wagle has stated that the government's priority is the country's...